Projected End Date for Indian Point Plant Comes into Clearer Focus

Neil Sheehan
Public Affairs Officer
Region I

April 30th will mark a decade since Entergy submitted a license renewal application to the NRC for the Indian Point nuclear power plant. During the intervening years, thorough NRC staff reviews and a complex hearing on the proposal by the Atomic Safety and Licensing Board, the quasi-judicial arm of the NRC, have moved steadily forward.

indianpointBut then came an announcement on Jan. 9 by Entergy, the plant’s owner, and New York state. Under an agreement reached between the two parties, Indian Point Unit 2 would permanently shut down by April 30, 2020, and Indian Point Unit 3 by April 30, 2021. (Indian Point Unit 1 ceased operations in 1974).

This represents an earlier retirement of the reactors than proposed in the company’s license renewal application, which sought an extension of Unit 2’s operating license to April 2033 and Unit 3’s to April 2035.

Entergy cited the low cost of natural gas and rising operating costs as primary factors in its decision. The company said it would instead pursue a license renewal for Unit 2 to 2024 and for Unit 3 to 2025 to allow operation until then in the event the plant’s power output is still needed.

Company officials offered assurances that there would be continued adherence to safety requirements for the remainder of the plant’s operational life. NRC inspectors will be on hand to independently verify that all safety commitments are being met.

The NRC has three full-time Resident Inspectors assigned to Indian Point. We also send specialist inspectors to the facility to assess such areas as security, radiation safety and reactor operator training.

Agency staff will also have to complete their license renewal reviews and the hearing process will have to be brought to a conclusion. With respect to the latter, a motion to withdraw the remaining contentions in the hearing process is expected today.

It will be essential for Indian Point employees to maintain a strong focus on safety no matter the plant’s eventual end date. It will be incumbent upon the NRC to ensure that is occurring.

 

 

 

 

 

 

 

 

 

3 responses to “Projected End Date for Indian Point Plant Comes into Clearer Focus

  1. Anonymous February 10, 2017 at 3:34 pm

    IP2 & IP3 is classic example of an utility can exploit federal bureaucracy, combined with staff granting time (by way of an additional FEIS) and other (convenient safety reviews for the utility’s benefit) till completion of which you can continue to operate. Do they really need a renewal…really!!

  2. Nikohl Vandel February 9, 2017 at 2:42 pm

    Thank you, and yes, ensure the highest quality of safety on the closing and that they pay for the mess it has become.

  3. annebeck58 February 8, 2017 at 6:35 pm

    Reblogged this on annebeck58 and commented:
    So glad this one is being closed.
    Now, it is time to shutter the rest of them; say goodbye to the Cartel!

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: