GAO and the Fake Licensees

Duncan White
Senior Health Physicist

The Government Accountability Office (GAO) published a report today on a “covert operation” they conducted to test the NRC and some states on the process of issuing licenses for possession and use of radioactive materials.

First some facts: GAO established a fake company and made three attempts to obtain a license. GAO was successful in only one case. As part of their operation, GAO then altered the license and placed orders for radioactive material with two companies that could have resulted in GAO receiving double the quantity of material authorized in the license. That quantity of material would have posed a higher potential risk than what was actually authorized in the unaltered license, and would have required additional security measures.

In the language of radioactive materials categories (see box), the fake GAO company had a valid license for a Category 3 quantity, but used a modified copy of that license to order a Category 2 quantity.

It is important to note that the public’s safety was never at risk because GAO never actually obtained radioactive material.

The license GAO obtained was granted by one of our Agreement States (the 37 states that regulate radioactive materials under agreements with us). After we learned of the GAO actions, we immediately made sure that the Agreement State knew the license was obtained under false pretenses and revoked it, and notified manufacturers and distributors of the revocation. We also made sure that the 36 other Agreement States knew about the issue.

Our next step was to figure out what went wrong. Working with the Agreement State that issued the license, we found that the licensing staff did not complete all the required steps of the pre-licensing procedures. In GAO’s other two attempts, the licensing officials who correctly denied GAO’s fake company a license – in another Agreement State and in an NRC regional office – did follow all the steps of those procedures.

Knowing the root cause helped us to focus our corrective actions. The NRC and all the Agreement States responded with steps to improve training and underscore the importance of following procedures. All licensing and inspection staff at the NRC and in the Agreement States completed this re-training in December 2015.

NRC and Agreement State officials also formed joint working groups to see what additional lessons can be gathered from the GAO operation. These groups have been meeting since January 2016. Among their tasks, the groups are reviewing the pre-licensing guidance and evaluating new strategies to improve license verification and transfer procedures for the quantity and type of material involved in the GAO sting.

The groups will also consider GAO’s specific recommendations. Once this work is completed, the NRC staff will present to our management and Commissioners any policy questions that emerge from the reviews, including whether we think changes are needed to the current security and tracking requirements for radioactive materials.

The NRC takes radioactive materials security very seriously. We participate with 13 other federal agencies on a U.S. Government task force that has evaluated the security of radiation sources in the U.S. over the past 10 years. This group has identified no significant gaps in source security and recommended no legislative changes.

GAO reccomend__HorizontalBased on this comprehensive, ongoing review, we believe current NRC regulations for licensing radioactive sources remain adequate for protection of safety and security, consistent with the risks they pose. Nonetheless, the NRC is doing what it can to see what lessons from the GAO operation can be applied to strengthen radioactive materials security.

More on Baffle Bolts

John Lubinski
Director, Division of Engineering
Office of Nuclear Reactor Regulation

We described degradation in baffle-former bolts at Indian Point Unit 2 in an April 27 blog post. The degraded bolts were discovered by Entergy, the plant operator, while inspecting the bolts during a refueling outage. Since then, PSEG, the operator of the Salem nuclear power plant in New Jersey, discovered some degraded bolts while inspecting the baffles of Unit 1.

To recap, the bolts hold in place a series of vertical metal plates. Known as baffle plates, they help direct water up through the nuclear fuel assemblies, where it is heated and subsequently used for power production. The baffle plates are attached to eight levels of horizontal plates called baffle-former plates, which are in turn connected to the reactor core barrel.

Because of these findings, the NRC has initiated its process for dealing with emerging issues to evaluate the extent of the problem and determine how best to address it. Here’s what we know so far:

We are confident this issue lacks an immediate safety concern that would lead us to shut down U.S. nuclear power plants or prevent the startup of plants in refueling outages.

We have been aware of the phenomenon. Degraded baffle-former bolts were detected in French reactors in the late 1980s and 1990s, and the NRC published an Information Notice in 1998 alerting the U.S. industry. The higher number of degraded bolts seen recently however, was unexpected.

The 1998 Information Notice prompted several plants to inspect their bolts, and some made adjustments to their baffles or replaced bolts as a result. NRC-approved guidance from the Electric Power Research Institute calls for visual and ultrasonic inspections during a certain period in a reactor’s lifespan. The current inspections at Indian Point and Salem resulted from this operational experience.

It’s important to note that if bolt parts come loose during normal operations and damage fuel, the condition will be detected by routine monitoring of radioactivity in the reactor coolant water. During refueling outages, plant operators look for debris on the bottom of the reactor vessel as another indication of potential issues. Even during an accident, the danger of core damage would be minimal. For these reasons, the NRC does not believe it necessary to shut down any additional plants and order immediate inspections.

Plants with degraded bolts are required to perform analyses and/or replace the damaged bolts before restarting. Missing bolt parts (such as a bolt head) must be accounted for or recovered, or the licensee must perform a “loose-parts evaluation” prior to restarting. The NRC staff will independently assess the root-cause and safety significance of the bolt degradation at each reactor and take appropriate regulatory action.

Indian Point 2 has replaced all of the failed bolts, plus an additional 51 “good” bolts to add additional safety margin. They intend to inspect all the baffle-former bolts again during the next refueling outage.

So how many plants might have this problem? Only Westinghouse-designed pressurized-water reactors with four reactor coolant loops have reported significant bolt degradation. Although there are 29 such plants in the United States, the issue appears to be further limited by two factors: The degraded bolts have all been of a certain type of stainless steel, and they’ve all been in reactors with baffles in a “downflow” configuration, meaning the water entering the reactor is pushed downward between the baffle and the core barrel, which creates more pressure across the plates and stress in the bolts.

There are only seven four-loop Westinghouse reactors at four sites with both the susceptible bolt material and a downflow configuration: Indian Point Units 2 and 3, Salem Units 1 and 2, D.C. Cook Units 1 and 2, and Diablo Canyon Unit 1. (Diablo’s Unit 2 has been reconfigured to an upflow baffle.) Our resident inspectors at D.C. Cook and Diablo Canyon have asked those sites to consider the recent findings and implications for their plants, including their plans for future bolt inspections. D. C. Cook Unit 2 observed 42 degraded bolts in 2010, and as a result replaced 52 bolts. Follow-up visual inspections in 2012 revealed no problems.

Bolt degradation starts to appear sometime after 25 “effective full-power years” of operation (based on actual operation, not calendar years since licensing). So the NRC-approved EPRI guidance advises PWR operators to inspect their baffle-former bolts sometime between 25 and 35 effective full-power years. The NRC requires the inspections as part of aging management plans for reactors with renewed licenses.

As a result of the findings at Indian Point 2, Entergy decided it will conduct detailed ultra-sonic testing of baffle-former bolts in Indian Point 3 during its next outage in spring 2017, instead of March 2019 as previously scheduled. Since Indian Point 3 has operated for a shorter time and has put less thermal stress on its bolts that would cause fatigue, waiting a year is acceptable.

PSEG had been conducting visual inspections every other outage, and because of their discovery of degraded bolts during the current inspection of Salem 1, they decided to conduct the ultrasonic test now rather than in 2023 as previously planned. PG&E indicated to the NRC that it will inspect the bolts on Diablo Canyon 1 during its next scheduled outage in spring 2017.

While the industry is reacting to the recent findings at Indian Point 2 and Salem 1, the NRC will continue to assess baffle-former bolt degradation for any potential implications to the rest of the U.S. commercial reactor fleet.

%d bloggers like this: