Entergy to NRC: Pilgrim Nuclear Power Plant To Cease Operations

Neil Sheehan
Public Affairs Officer
Region I

pilgOver the past few years, five reactors have permanently stopped operation earlier than anticipated and began the process of decommissioning. A sixth will soon be joining that list, it was announced yesterday. Entergy, owner of the Pilgrim nuclear power plant, announced its plan to stop operations at the Plymouth, Mass., facility no later than June 1, 2019. The nuclear plant in Oyster Creek previously announced it was shutting down in 2019.

Entergy has emphasized to the NRC its commitment to safe plant operations until Pilgrim’s control rods are inserted for the last time and the unit is shut down. The company has also told us it intends to get ready for and support NRC inspection activities associated with the plant’s recent transition to Column 4 of our Action Matrix.

The NRC will continue to conduct inspections and provide oversight consistent with that required of a plant in that status, with a team inspection expected sometime in 2016.

More broadly, the agency will keep close watch on Pilgrim’s performance through the end of its operational life. Additional information on the agency’s oversight activities at the plant are available on the NRC’s website.

There are more than a dozen units in some stage of decommissioning under NRC oversight.  The NRC has traditionally used operating reactor regulations for plants undergoing decommissioning, which requires the plants to seek exemptions when the regulations for operating reactors are no longer relevant or appropriate.

While this approach is sound from a safety standpoint, the Commission has directed NRC staff to initiate a process for developing a reactor decommissioning rulemaking, with a final rule to be issued by early 2019. For information on decommissioning can be found on the NRC website.

 

 

 

A Decommissioning of a Different Sort: NRC Resident Inspector Office at Vermont Yankee Shuts Down

Neil Sheehan
Public Affairs Officer
Region I

VYResidentOfficeClose 7-2015Something happened last week at the Vermont Yankee nuclear power plant that might not merit headline news but is nonetheless worth highlighting: The lights were turned off for the last time in the NRC’s Resident Inspector office at the site.

As is well known by now, Vermont Yankee permanently ceased operations last December, bringing to a halt power production that had begun in November 1972. Since 1978, when the Resident Inspector program was launched, the NRC has had two such inspectors assigned to the site.

Among other things, these inspectors have kept close watch on day-to-day activities, responded to events, performed inspections and reviews and served as a vital conduit of information to the NRC. But commensurate with the reduced safety risk associated with a permanently shutdown reactor, the NRC has ended its daily inspector presence.

The NRC had kept a Resident Inspector at the Vernon, Vt., site to allow us to maintain on-site scrutiny during the early stages of the transition from an operating plant to one entering decommissioning. (Vermont Yankee will be using the SAFSTOR approach, which will involve placing the unit in storage for many years before embarking on major decontamination and dismantlement work.)

Although the Resident Inspector office has closed, NRC’s review activities have not come to a halt. Rather, the agency will continue to perform inspections at the plant on a periodic and targeted basis.

For instance, whenever there is major work taking place, such as the demolition of a nuclear-related building or the removal of spent fuel stored in the plant’s spent fuel pool into dry casks, an NRC inspector will be present. In addition, NRC will conduct inspections at the site at regular intervals to check on the plant’s safety status and any key developments until all spent fuel has been removed from the site and the plant’s NRC license is terminated.

Anyone seeking to contact the NRC regarding Vermont Yankee can continue to do so by calling the agency’s Region I Office via its toll-free phone number at 1-800-432-1156 and asking for the Division of Nuclear Materials Safety or by e-mail at OPA1@NRC.GOV .

Vermont Yankee is not unique with respect to this change involving the Resident Inspectors assigned to the plant. Three other plants that have shut down in recent years have also seen this changeover.