NRC Inspectors: Free to Inspect

Diane Screnci
Senior Public Affairs Officer
Region I

We often talk about having NRC Resident Inspectors at each commercial nuclear plant acting as the eyes and ears of the agency on site. It’s important to understand how they go about their business.

Paul Cataldo
Paul Cataldo

On a daily basis, resident inspectors are attending meetings, walking down equipment, monitoring major work activities, reviewing paperwork, and talking to control room operators and plant workers. When an event occurs at a plant, the resident inspectors are in the control room, watching how operators and the plant respond. They provide first-hand knowledge of what’s going on at a plant to regional management on an on-going basis. Inspectors often work business hours, but they’re required to work evenings, weekends and overnight hours, too.

NRC inspectors, including region-based specialists, have “unfettered access,” so they can go anywhere and watch any activity they choose. NRC regulations specify that NRC inspectors must have immediate unfettered access, although inspectors must comply with applicable access control measures for security, radiological protection and personal safety. That means if an inspector wants to enter a radiologically controlled area, he or she is allowed to, but first must follow the radiation protection requirements for the area.

“My job is to ensure the company is in compliance with our regulations and their operating license, which provides reasonable assurance that the plant is safe. One approach I use is the “trust but verify” method,” says Paul Cataldo, the NRC Senior Resident Inspector at Seabook Station in New Hampshire. “In essence, having access to any document, equipment or personnel on-site, without asking permission or the licensee having prior knowledge of a request, gives us confidence regarding the integrity of the information we use during our inspections.”

Plant workers are also prohibited from announcing that an NRC inspector is at the plant or in a particular area. It’s a violation of NRC requirements and over the years we have cited plants when workers tipped off their co-workers that inspectors were on-site.

We rely on our ability to perform announced and unannounced inspections to independently evaluate plant performance. Without unfettered access, our ability to carry out our mission could be impacted.

Additional Scrutiny at Pilgrim Nuclear Power Plant Set to Continue

Neil Sheehan
Public Affairs Officer
Region I

Update: As a follow-up, the NRC is launching a Special Inspection today (Monday, Feb. 2) at the Pilgrim nuclear power plant in response to the shutdown that occurred at the Plymouth, Mass., facility on Jan. 27. The six-member team will review equipment issues experienced during the shutdown, including the partial loss of off-site power. The results of the NRC inspection will be made publicly available within 45 days of the inspection’s completion.

Last fall, a team of NRC inspectors was tasked with evaluating whether issues at the Pilgrim nuclear power plant that triggered increased agency oversight had been satisfactorily addressed. That team has now returned its findings in the form of a newly issued inspection report.

pilgrimAnd the answer – at least at this point in time – is that Entergy, the Plymouth, Mass., plant’s owner, still has some more work to do.

Specifically, although the eight-member team has determined that, in general, the company’s problem identification, root cause evaluation and corrective action plans were adequate, it has identified deficiencies in the implementation of corrective action plans, as well as in understanding of the issues’ causes.

In its report, the team cites several examples where fixes were not completed as intended or were closed prematurely.

As a result, per agency protocols, the NRC is assigning two “parallel” “white” (low to moderate safety significance) inspection findings to Pilgrim. The findings will administratively replace two “white” performance indicators that initially led to the plant receiving additional scrutiny.

The net effect will be the plant will continue to receive heightened attention until the NRC can perform a follow-up team inspection and is satisfied the concerns have been resolved. The NRC will conduct that additional inspection once Entergy notifies the agency of its readiness for it.

To back up for a moment, the Pilgrim plant’s performance indicator for Unplanned Scrams (shutdowns) with Complications crossed the threshold from “green” to “white” following the third quarter of 2013. Then, in the fourth quarter of last year, the performance indicator for Unplanned Scrams per 7,000 Hours of Operation also changed to “white,” something that occurs if a plant has more than three such shutdowns during the designated period.

This placed Pilgrim in the Degraded Cornerstone Column of the Action Matrix used by the NRC to assess plant performance.

Pilgrim has not had any unplanned scrams since October 2013, and the performance indicators discussed above are currently “green.” But the assignment of the white findings will keep the plant in the Degraded Cornerstone Column pending successful completion of the supplemental inspection.

The NRC intends to discuss the inspection results during the Annual Assessment meeting for the plant. That meeting will likely take place in March near the plant, but a date, time and location have not yet been firmed up.

 