Fort Calhoun: Heat-Up, But Not Start Up

Lara Uselding
Public Affairs Officer
Region IV
 

Following a two-and-a-half year shutdown, Omaha Public Power District (OPPD) is ready to heat up Fort Calhoun’s reactor coolant system to inspect for any leaks. Heat-up is not the same as restarting the plant. The plant has been shut down since April 2011 for a refueling outage. The outage was extended due to historic Missouri River flooding followed by an electrical fire and other restart complications.

Fort Calhoun Station is heating up the reactor coolant system to ensure that the pipes carrying high pressure water or steam do not have leaks. Rather than heating up the reactor using the fission process, OPPD will use the reactor coolant pumps to heat up water and get steam flowing through the system. NRC inspectors are on site to observe licensee activities as well as perform independent inspections to ensure there are no leaks.

In early October, OPPD submitted a license amendment request seeking NRC permission to use a different methodology to evaluate high-pressure pipe breaks. OPPD has to demonstrate that if a high pressure pipe ruptures, that it would not negatively impact nearby equipment.

On Oct. 25, after reviewing public comments and additional information provided by the licensee, NRC approved this license amendment. OPPD did plant modifications and has performed calculations that show a potential pipe rupture will not affect nearby equipment. NRC inspectors are independently verifying the licensee’s analysis and modifications.

In addition, the staff has finalized its review of OPPD’s request to be exempt from the NRC’s fatigue rule which sets work hour limits in support of plant heat-up activities. The NRC’s fatigue rule puts limits on certain workers’ weekly hours to protect against fatigue. For example, during a refueling outage, a worker is allowed to work up to 72 hours every week versus an average of 54 hours over six weeks.

Before the NRC issued the exemption, the staff ensured that workers will have sufficient time to rest prior to working additional hours in support of the heat-up activities.

In addition, the NRC is continuing independent review of the remaining restart checklist items.

Next steps include preparations for the next public meeting whereby staff will update the public on NRC’s oversight status. No decision about restart will be made at that meeting.

Sandy’s One-Year Anniversary Serves as A Reminder

Neil Sheehan
Public Affairs Officer
Region I
 

Tomorrow marks the one-year anniversary of one of the worst coastal storms in U.S. history. Hurricane Sandy made landfall just north of Atlantic City and left billions of dollars in damages in its wake. A year later, impacted areas of New Jersey and New York are continuing efforts to recover from the pounding the storm delivered.

The one-year anniversary of Hurricane Sandy serves as a reminder of the devastation the storm brought to neighborhoods along the Atlantic Coast.
The one-year anniversary of Hurricane Sandy serves as a reminder of the devastation the storm brought to neighborhoods along the Atlantic Coast.

The NRC focused on the safety of nuclear power plants in the storm’s path as Sandy bore down on the region, dispatching additional inspectors to augment the resident inspectors at some of the potentially affected sites to provide for 24-hour coverage. In addition, the agency shifted to an elevated response mode that involved the activation of the Incident Response Centers in our Region I and II offices, and the Operations Center at our Headquarters office.

Throughout the event, the NRC also worked closely with state, county and federal partners, including FEMA.

As the storm struck, the plant closest to the eye of the hurricane, Oyster Creek in New Jersey, was shut down at the time but nonetheless had to cope with flooding conditions at its water intake structure and a temporary loss of off-site power. Three other reactors, meanwhile, either shut down or were knocked out of service by the storm’s effects.

At no time was the safety of these plants or others in the Northeast compromised, reflecting the high level of training for their operators, the hardened nature of the structures at the sites and preparations leading up to the storm’s arrival.

Still, there are always lessons to be learned from such events. For many nuclear power plants, the storm has led to a fresh evaluation of severe weather guidelines. These guidelines cover such areas as when a plant needs to begin powering down when wind speeds associated with a severe storm begin to impact a facility.

As for the NRC, we continue to assess the ability of plants to withstand severe flooding as part of our post-Fukushima reviews. Each plant is required to complete a flooding hazard re-evaluation to confirm the appropriateness of the hazards assumed for the site and the ability to protect against them.

Plant owners are required to use updated methods and information, with the results determining whether any additional regulatory actions are needed. More information on the NRC’s post-Fukushima reviews is available on the agency’s website.

Thus far, 2013 has seen low levels of hurricane activity, but Sandy will stand as a powerful reminder of the need for vigilance when it comes to storm preparations.